A diagram with three panels. In the first, a large box labelled supply chain management contains a smaller box labelled sourcing and procurement, which is the placement CSCMP’s definition implies. In the second, two boxes of equal size labelled procurement and supply and supply chain management sit side by side with an arrow between them, which is the placement CIPS’s wording implies. In the third, a single narrow box labelled award, entry into and management of a contract, which is the definition in the UK Procurement Act 2023.
What is the difference between procurement and supply chain management?
Procurement is accountable for the terms on which supply is available. Planning is accountable for the quantities and dates drawn against those terms. That split survives every definition below, and it is the one you can actually assign to people.
It needs saying that way because the organisations whose job it is to define these words do not agree, not with the usual shorthand that procurement is the buying and the supply chain is everything else, and not with each other.
Start with the two that matter most. CSCMP’s official definition says Supply chain management encompasses
the planning and management of all activities involved in sourcing and procurement, conversion, and all
logistics management activities
(CSCMP).
That puts procurement firmly inside, as one of three named activity groups. ASCM’s dictionary says supply
chain management is the design, planning, execution, control, and monitoring of supply chain activities
with the objective of creating net value, building a competitive infrastructure, leveraging worldwide
logistics, synchronizing supply with demand, and measuring performance globally
(ASCM), a definition that never mentions buying at all.
Then CIPS, the chartered body for the buying side, writes that Procurement and supply professionals should
become increasingly involved in SCM, ideally playing a leading role in its development wherever possible
(CIPS). You cannot become increasingly
involved in something you are already a part of. That sentence places procurement alongside supply chain
management, not within it.
And UK statute ignores the whole frame. The Procurement Act 2023 defines the word in eleven words:
“procurement” means the award, entry into and management of a contract;
(Procurement Act 2023, section 1). No suppliers, no
markets, no supply chain. Three things you do to a contract.
No professional body puts the split that way, because they cannot agree on a form of words at all. And the reason it matters is not tidiness: a buying function judged on unit price and a planning function judged on service will optimise against each other, and both will hit their targets.
| Procurement | Planning, the supply chain side | |
|---|---|---|
| Accountable for | The terms on which supply is available | The quantities and dates drawn against those terms |
| Of the five decisions below, it owns | Supplier; price and terms | Quantity; date |
| A body’s own description of its scope | A thirteen-step cycle from defining the need to asset management (CIPS) | Planning and managing sourcing, conversion and all logistics (CSCMP) |
| Usually measured on | Price, savings, supplier performance | Service level, inventory, forecast error |
| Statutory clocks it carries in India | 180-day input tax credit; 45-day MSME payment | None of these |
| Its certifying bodies | CIPS, and ISM’s CPSM | ASCM’s CPIM and CSCP |
The “usually measured on” row is how these functions are commonly judged rather than a finding from a source. Everything else in the table is either quoted below or is the five-decision split this article argues for.
On this page
1. The bodies that own the words do not agree.
What is procurement?
Procurement is everything involved in getting goods and services from outside the organisation: working out what
is needed, finding who can supply it, agreeing the terms, placing the order and managing the relationship
afterwards. CIPS, the chartered body for the discipline, draws the cycle from defining a business need all the
way to asset management (CIPS). In the narrowest published definition, UK statute reduces it to
the award, entry into and management of a contract
(Procurement Act 2023).
What is supply chain management?
Supply chain management is the coordination of everything that moves goods from source to customer, including
the buying. CSCMP’s definition is the one most quoted: it encompasses the planning and management of all
activities involved in sourcing and procurement, conversion, and all logistics management activities
(CSCMP). ASCM’s dictionary frames it as the design, planning, execution, control, and monitoring
of supply chain activities
(ASCM) and does not mention buying at all, which is the first sign
of the problem this article is about.
Is procurement the same thing as purchasing?
Four bodies, four different answers.
CIPS splits them by time horizon. The main difference is that procurement is a long-term approach to
acquiring goods and services, and purchasing is the short-term direct purchasing of products and servings
(the typo is theirs) and purchasing is fulfilling the transaction only and is very much a reactive and
transactional approach
(CIPS).
ASCM splits them by strategy and execution. Generally speaking, procurement entails creating a
strategy for acquiring goods and services that meet your company’s long-term needs, while purchasing is about
executing that strategy through specific transactions
(ASCM). Close to CIPS, but the axis is different:
plan versus do, rather than long versus short.
The UN system does not split them at all. In UNOPS’s rules, purchase is simply one of several methods by
which procurement happens: procurement is the acquisition of property, plant and/or equipment, goods, works
or services through purchase, hire, lease, rental or exchange from any source other than UN system
organizations
(UNOPS Procurement Manual).
Purchasing is not a lesser activity than procurement here. It is one way of doing it, next to hiring and
leasing.
And CSCMP treats them as the same thing. Its five-process model of supply chain management labels one
process Procurement and then describes it as the stage where the buy process focuses on the purchase of
required raw materials, components, and goods
(CSCMP), the
exact equation that CIPS’s definition page exists to deny.
Where does sourcing sit?
Worse. The two biggest bodies put sourcing in different places in the hierarchy, and the orderings are incompatible.
ASCM’s own CPIM courseware states that Purchasing includes sourcing, ordering, and scheduling
deliveries
(ASCM CPIM Learning System).
Sourcing is a component of purchasing. CIPS has purchasing as the narrow transactional floor of a much wider
procurement cycle that includes sourcing, so sourcing sits above purchasing, not inside it. Both are
published, current and authoritative. They are also incompatible.
The definitions of sourcing itself do not match either. ASCM’s dictionary calls it The process of
identifying a company that provides a needed good or service
(ASCM): finding
a supplier. CIPS says Sourcing is the locating of products or services that are required for your
organisation to operate
(CIPS): finding a product. One
is about who, the other about what.
And the body whose entire name is built on the phrase supply management, the Institute for Supply Management, publishes its glossary as a priced book, so I could not check its definition at all.
2. Each discipline puts the other one inside itself.
This is the part that should settle the question, because it shows the question cannot be settled.
CSCMP’s definition of supply chain management, quoted above, makes sourcing and procurement
one of
three peer activity groups alongside conversion and logistics management. Further down the same
page, its definition of logistics management says logistics is that part of supply chain management that
plans, implements, and controls the efficient, effective forward and reverses flow and storage of goods,
services and related information between the point of origin and the point of consumption in order to meet
customers’ requirements
(again, the typo is theirs) and then adds: To varying degrees, the logistics
function also includes sourcing and procurement, production planning and scheduling, packaging and assembly,
and customer service
(CSCMP).
Read those two definitions together. Procurement is a peer of logistics, and procurement is inside logistics. The same sentence appears again on CSCMP’s own careers FAQ page (CSCMP), so this is settled house text rather than a stray edit.
Now look at it from the other side. CIPS publishes a thirteen-step procurement cycle. Step 10 is
Step 10: Warehouse, logistics and receipt
, and the cycle runs on past delivery to
Step 13: Asset management
(CIPS).
Logistics is a step inside procurement.
So CSCMP’s logistics contains procurement, and CIPS’s procurement contains logistics. Each body nests the other’s discipline inside its own, and both are describing the same companies.
Text version
On the left, CSCMP’s logistics management definition is drawn as a large box labelled logistics with a smaller box inside it labelled sourcing and procurement. On the right, CIPS’s thirteen-step procurement cycle is drawn as a large box labelled procurement with a smaller box inside it labelled step 10, warehouse, logistics and receipt. The two diagrams are mirror images, which is the point: each discipline’s own body places the other discipline inside it.
3. Why the boundary moved, and kept moving.
The disagreement is not carelessness. The function renamed itself twice inside one working lifetime, and the names did not replace each other so much as accumulate.
The clearest statement of the sequence is in a peer-reviewed abstract: the strategic role of purchasing
has recently evolved and expanded from ‘‘buying’’ to ‘‘procurement’’ and ‘‘supply management’’
, and the
paper attributes the shift to The growing importance of supply chain management
(Paulraj, Chen and Flynn).
So supply chain management did not absorb purchasing. Its arrival caused purchasing to rename itself twice.
Meanwhile the parent term was multiplying. One study examines 166 definitions of SCM that have appeared in
the literature to determine important components of an integrated definition of SCM
(Stock and Boyer). Not 166 papers: 166 definitions.
And this is not only an academic tidiness problem. As one review puts it, The corollary of this is that a
lack of definitional consistency and a common understanding is an inhibitor to the successful adoption of SCM
thinking in practice
(Sweeney).
The vocabulary problem is an adoption problem.
The sharpest illustration is in a journal’s own anniversary issue, where the editors of the Journal of
Purchasing and Supply Management each wrote a separately signed section. In section 2.5, Zsidisin writes that
purchasing and supply management as an academic discipline is a critical sub-set of supply chain
management
. In section 2.7, Knight writes that PSM research is not just a specialism within SCM.
Both are in one paper
(the JPSM editors’ retrospective).
If the editors of the field’s own journal cannot agree inside one document, the question you typed into a search box was never going to have one answer.
4. The boundary that matters: five decisions, not two words.
Here is the practical move. Stop asking which word covers which activity, and ask who decides what. Every definition quoted above, however it draws its boundary, is made of the same five decisions. Those decisions are the thing you can actually assign, measure and get wrong.
| The decision | Where it is recorded | What goes wrong when it is split badly |
|---|---|---|
| Specification | The drawing or specification revision | A spec written around one supplier, so the sourcing is settled before procurement is involved |
| Supplier | The approved vendor list | A supplier chosen on unit price whose lead time wrecks the buffer the planner has to hold |
| Price and terms | The purchase order terms and the contract’s payment clause | Terms agreed without the cash and tax consequences in section 5 being checked |
| Quantity | Minimum order quantity, lot size and reorder point in the item master | An order quantity set to hit a price break, so the stock is bought for the discount |
| Date | The planning lead time in the MRP record, against the contractual lead time | A date promised to the plant that the contract never obliged the supplier to meet |
Text version
Five boxes stacked vertically, one per decision: specification, supplier, price and terms, quantity, date. Specification is shaded and marked shared, because it is set upstream of both sides and constrains everything below it. A bracket beside supplier and price and terms is labelled procurement, the terms on which supply is available. A bracket beside quantity and date is labelled planning, the quantities and dates drawn against those terms.
The recording locations are where to go and look; they are typical names, and your system may call them something else. The last column is the point. Every failure in it is a handover failure rather than a competence failure, and none of them is fixed by deciding whether procurement is part of the supply chain.
So here is the test. Pull those five records for your three highest-spend items. Where two of them disagree (a contractual lead time of six weeks against a planning lead time of three, say), you have found the split, and you have found it in about an hour.
What is your buying function actually measured on?
The decisions tell you who owns what. The second half of the diagnostic is what the buying function is being
judged on, and there is a published ladder for it. A study that collects data from 32 firms in two
markets
found their purchasing departments reveal four stages of purchasing evolution: passive (price
focused), independent (cost-focused), supportive (solution/innovation focused), and integrative (strategy
focused)
(Paesbrugghe and colleagues).
Read a job description, a bonus scheme or a monthly report against those four words. A function at the passive stage is measured on price, and no amount of definitional clarity will move it: that is a measurement problem wearing a vocabulary problem’s clothes. A function at the integrative stage is in the conversation where specifications and quantities get set, which is where the handover failures in the table above stop happening.
This is also the one part of the question the research can answer. Across 148 companies, a study found
a positive impact was found of cross-functional integration and functional coordination on purchasing
performance, and of purchasing performance on firm performance
(Foerstl and colleagues). The study combined its own survey data with
secondary firm-performance data, so the performance side is not self-reported. The thing that predicts
performance is not where you draw the line. It is whether the people on either side of it talk to each other.
That is also why the quantity and date decisions cannot be made well in isolation: they run on a demand forecast, and the reasons forecasts fail are mostly not the forecaster’s fault.
5. In India, procurement carries rules that planning does not.
If you want a boundary with teeth rather than a definitional one, here it is. Two of these land on whoever agrees the payment terms and have no equivalent on the planning side. The third runs the other way, and binds you only when you sell to government.
The 180-day GST input tax credit reversal rule.
Under section 16 of the CGST Act, in force from 1 July 2017 (CGST Act, section 16), input tax credit is not simply yours once you have the invoice. If you do not pay the supplier, you give the credit back.
The Act provides that where a recipient fails to pay to the supplier of
goods or services or both, other than the supplies on which tax is payable on reverse charge basis, the amount
towards the value of supply along with tax payable thereon within a period of one hundred and eighty days from
the date of issue of invoice by the supplier, an amount equal to the input tax credit availed by the recipient
shall be paid by him along with interest payable under section 50, in such manner as may be prescribed
(CGST Act, section 16).
In other words: a 180-day clock runs on every invoice where you have claimed the input tax credit; the proviso excludes supplies taxed on reverse charge, where you pay the tax yourself and there is no supplier-payment condition to fail. On everything else, the person who agreed the payment terms is seldom the person watching the clock.
The credit comes back when you pay. The recipient shall be entitled to avail of the credit of input tax
on payment made by him to the supplier of the amount towards the value of supply of goods or services or
both along with tax payable thereon
(CGST Act, section 16).
The 45-day MSME payment rule, and the interest that follows.
Shorter, and it carries interest. Sections 15 to 24 of the MSMED Act, 2006 govern delayed payment to micro and small enterprises.
I could not reach the Act’s own text, so what follows is the Ministry of MSME’s description of it rather than
the statute. The ministry states that The buyer is liable to pay compound
interest with the monthly rests to the supplier on the amount at the three times of the bank rate notified by
RBI in case he does not make payment to the supplier for his supplies of goods or services within 45 days of
the acceptance of the goods/service rendered
(MSME Samadhaan). Three times the Reserve
Bank’s bank rate, compounded monthly, is not a late-payment nuisance charge. It is a reason to know which of
your suppliers are micro or small enterprises before you negotiate terms.
| Clock | Runs from | Deadline | If you miss it | Applies to |
|---|---|---|---|---|
| MSMED Act, ss. 15-24 (as the ministry describes it) | Acceptance of the goods or service | 45 days | Compound interest, monthly rests, at three times the RBI bank rate (MSME Samadhaan) | Micro and small enterprises |
| CGST Act, section 16 | Date of the supplier’s invoice | 180 days | The input tax credit you claimed is added back, with interest under section 50 (CGST Act) | Any invoice where you claimed the credit, except reverse-charge supplies |
The shorter clock carries the harsher penalty, and it is the one with no line on most payables reports.
Make in India local content: Class-I and Class-II thresholds.
This one runs the other way from the two clocks, and it is worth being exact about. The Make in India order
constrains the buyer only when the buyer is government: a ‘Procuring entity’ means a Ministry or
department or attached or subordinate office of, or autonomous body controlled by, the Government of India and
includes Government companies as defined in the Companies Act.
(Public Procurement (Preference to Make in India) Order, revised 19 July 2024) If you are a private manufacturer or
distributor, the order imposes nothing on your own purchasing. It matters when you are the one bidding.
The thresholds are 50% and 20% local content: 5. Minimum local content: The ‘local content’ requirement to
categorize a supplier as ‘Class-I local supplier’ is minimum 50%. For ‘Class-I I local supplier’, the ‘local
content’ requirement is minimum 20%.
(Public Procurement (Preference to Make in India) Order, revised 19 July 2024)
The order’s own text reads Class-I I local supplier
for the second class.
The purchase preference does not let a local supplier win at a higher price, which is the common misreading.
The margin is an eligibility band, not a price premium: it is the maximum extent to
which the price quoted by a “Class-I local supplier’’ may be above the L1 for the purpose of purchase
preference
, and The margin of purchase preference shall be 20%.
Within that band, First
purchase preference has to be given to the lowest quoting ‘Class-I local supplier’, whose quoted rates fall
within 20% margin of purchase preference, subject to its meeting the prescribed criteria for award of
contract as also the constraint of maximum quantity that can be sourced from any single supplier.
(Public Procurement (Preference to Make in India) Order, revised 19 July 2024)
And that supplier wins only by coming down to the lowest price: In case such lowest eligible ‘Class-I local supplier’ fails to match the L1 price, the ‘Class-I local
supplier’ with the next higher bid within the margin of purchase preference shall be invited to match the L1
price and so on and contract shall be awarded accordingly.
(Public Procurement (Preference to Make in India) Order, revised 19 July 2024)
Nor does matching win the whole order. On a divisible tender the government’s own model document says If
L-1 is not a ‘Class-I local Supplier’, 50% of the order quantity shall be awarded to L-1. After that, the
lowest bidder among the ‘Class-I local Supplier’ whose quoted price falls within the margin of purchase
preference shall be invited to match the L-1 price for the remaining 50% quantity
(Model Tender Document for Procurement of Goods, Department of Expenditure).
Two further limits before anyone builds a bid around it. Small buys are out: procurement where the estimated
value to be procured is less than Rs. 5 lakhs shall be exempt from this Order.
And the evidence burden sits
on the supplier rather than the buyer above ten crore rupees, where the class claimed has to be certified
from the statutory auditor or cost auditor of the company (in the case of companies) or from a practicing
cost accountant or practicing chartered accountant (in respect of suppliers other than companies)
. Get the
class wrong and a penalty upto 10% of the contract value may be imposed
, though contract once
awarded shall not be terminated on this account.
(Public Procurement (Preference to Make in India) Order, revised 19 July 2024).
That order runs to several pages of defined terms, including what a procuring entity is, and never defines procurement itself. In this order at least, Indian policy defines the buyer rather than the activity.
6. What the gap between price and cost is worth.
The reason any of this matters is that a buying function judged on unit price and a planning function judged on service will optimise against each other, and both will hit their targets.
The measurable version of that argument is the total cost of ownership literature, which prices what a
purchase actually costs rather than what it sells for. One study applied it to selecting airlines for 56
destinations at a single firm and reports: We apply this methodology to the real life case study of
selecting airlines for 56 destinations at Alcatel Bell and have obtained TCO savings of 19.5%.
(Degraeve, Labro and Roodhooft).
A second study by the same group across three industrial component groups reports Possible savings of
between 6% and 14% of the total cost of ownership of the current purchasing policy are obtained for the three
cases.
(Degraeve, Labro and Roodhooft).
Modelled saving from pricing a purchase on total cost rather than price
Modelled saving against current purchasing policy
Two cautions before you quote those numbers at anybody. Both are optimisation results computed against the
firm’s existing purchasing policy, not audited savings banked afterwards: the second paper’s own words are
Possible savings
(Degraeve, Labro and Roodhooft). And all three figures come from one research group, so the right reading is that the
gap is large, not that it is 19.5%.
The other half of the evidence is about status rather than method. A study of 221 US manufacturers set out to test the
claim properly, having first noted that claims of the strategic role of purchasing have not been fully
subjected to rigorous theoretical and empirical scrutiny. Extant research has remained largely anecdotal and
theoretically under-developed.
(Chen, Paulraj and Lado), worth
remembering when somebody asserts the strategic importance of buying as though it were settled.
7. Which job are you being offered?
Some readers arrive at this question choosing between two roles rather than organising a department, so here is the version of the answer that helps with that.
The four-stage ladder above is the thing to read a job description against. A role that reports savings against last year’s prices is a passive or independent purchasing role whatever the title says. A role that is asked for solutions and supplier innovation is at the supportive stage. A role sitting in the strategy conversation is integrative, and those are rare enough that the posting will usually say so by naming the people you would present to.
For the planning side, the tell is which of the five decisions in section 4 you would own. A planner who sets quantities and dates but inherits suppliers and terms has a narrower job than the title suggests. A procurement role that inherits specifications is in the same position from the other direction.
The two paths also have different gates: CIPS on the buying side, ASCM on the planning side, ISM on the buying side in North America. I have not sourced the syllabuses here, so treat that as orientation rather than advice, but whichever body’s vocabulary your prospective employer uses is a fair guess at which exam they will fund.
And the one-line distinction for an interview is the one at the top of this article: procurement is accountable for the terms on which supply is available, planning for the quantities and dates drawn against them. That sentence is mine, not a professional body’s, which, given everything above, is about as much authority as anyone’s gets here.
Limits: where this does not apply.
Three honest ones.
The definitional disagreement is a feature of English-language professional bodies. The sources here are CIPS, ASCM, CSCMP, ISM, the UN and UK statute. Bodies in other languages and legal systems may be more consistent; I did not check, and the Indian picture is thinner than it should be because the Department of Expenditure’s own manuals were unreachable.
The evidence on integration is correlational. The 148-company study combined survey and secondary performance data, which is better than self-reported performance, but it does not establish that integrating procurement and planning causes the performance. Firms that are good at one tend to be good at the other.
The India section is incomplete and dated in places. Thresholds move by notification rather than by amendment, which is why the MSME interest here is written as three times the bank rate and not as a percentage. Everything here carries the date the source showed; check anything load-bearing against the gazette before you act on it.
Where to start.
In order of what they are worth, not what they cost.
- Write the five decisions on one page with a name against each. Specification, supplier, price and terms, quantity, date. An afternoon, and the gaps are usually visible before you finish.
- Find out which of your suppliers are micro or small enterprises. The 45-day clock and the three-times-bank-rate interest apply to them and not to others, and nobody can act on that without the list.
- Put the 180-day input tax credit clock on the same report as the payables ageing. The two numbers are already in your system and are rarely read together.
- Ask which stage your buying function is at, against the four stages in section 4. If the answer is that it reports savings against last year’s prices, that is the thing to change, not the org chart.
- Stop arguing about the words. No decision in your business depends on whether procurement is a subset of supply chain management, and none of it is an optimisation either, and the bodies that certify both professions cannot agree on it anyway.
Frequently asked questions.
Is procurement part of supply chain management?
Depending on which body you ask, yes, no, or the question does not apply. CSCMP’s definition names
sourcing and procurement
as one of three activity groups inside supply chain management
(CSCMP). CIPS writes that
procurement professionals should become increasingly involved in SCM
, which places them outside it
(CIPS). The Procurement Act 2023 defines
procurement as the award, entry into and management of a contract
and never mentions supply chains
(Procurement Act 2023).
What is the difference between procurement and purchasing?
CIPS separates them by time horizon, calling purchasing the short-term direct purchasing of products and
servings
and procurement a long-term approach
(CIPS). ASCM separates them by
strategy versus execution (ASCM). The UN system does
not separate them at all, treating purchase as one method of procurement alongside hire and lease
(UNOPS).
In practice, use whichever your own organisation uses and define it once in writing.
Is sourcing inside purchasing, or inside procurement?
Both positions are published and they are not compatible. ASCM’s CPIM courseware states that Purchasing
includes sourcing, ordering, and scheduling deliveries
(ASCM): sourcing
inside purchasing. CIPS runs the other ordering: purchasing is the transactional floor and sourcing is a step
of the wider procurement cycle above it
(CIPS).
Does procurement include logistics?
CIPS’s thirteen-step procurement cycle includes Step 10: Warehouse, logistics and receipt
(CIPS). CSCMP’s logistics definition
says the logistics function also includes sourcing and procurement, production planning and scheduling,
packaging and assembly, and customer service
(CSCMP). So each contains
the other, depending on whose definition you read.
Which pays more, procurement or supply chain?
This article has no sourced salary data, so it will not guess at numbers. What it can say is what the pay tracks on each side, because that follows from the decisions. On the buying side it is the spend you are trusted with and the maturity stage you work at: a role reporting savings against last year’s prices is measured differently from one in the conversation where specifications get set. On the planning side it is the scope you cover (one plant, a network, or a whole chain) and how many people depend on your numbers. The same job title covers both the passive and the integrative version, so read the responsibilities and ignore the title.
Which qualification should I do, CIPS, CPIM or CPSM?
They sit on different sides of the boundary: CIPS and ISM’s CPSM on the buying side, ASCM’s CPIM and CSCP on the planning side. This article has not checked the syllabuses, so the useful heuristic is the cheap one: whichever body’s vocabulary your employer already uses is the exam they are most likely to pay for.
Who owns the boundary when there is no procurement function, just a buyer?
Then one person holds all five decisions and the handover failures in section 4 cannot happen, which is a genuine advantage of being small, and the thing most often lost when a company grows. The useful move at that size is to write the five decisions down anyway, because the split happens by accident when the second buyer is hired.
How many days do I have to pay an Indian supplier?
Two clocks, and they are different. If the supplier is a micro or small enterprise, 45 days from acceptance, after which compound interest at three times the Reserve Bank’s bank rate applies (MSME Samadhaan). Separately, where you have claimed input tax credit and the supply is not taxed on reverse charge, failing to pay within 180 days of the invoice date means that credit is added back with interest under section 50 (CGST Act, section 16, in force from 1 July 2017).
What local content do I need to sell to an Indian government buyer?
Minimum 50% to be a Class-I local supplier and minimum 20% for Class-II. The 20% margin of purchase preference is an eligibility band, not a price premium: a Class-I supplier quoting up to 20% above the lowest bid is invited to match that lowest price, and wins only if it does; on a divisible tender, for half the quantity. Above ten crore rupees the class has to be certified by an auditor or a practising accountant, and a wrong claim carries a penalty of up to 10% of contract value (Public Procurement (Preference to Make in India) Order, revised 19 July 2024). Check the current order before bidding; these figures carry the July 2024 revision date.
Sources.
27 references
- SCM Definitions and Glossary of Terms CSCMP, Council of Supply Chain Management Professionals
- Supply Chain Management - SCM ASCM, Association for Supply Chain Management
- Supply Chain Management CIPS, Chartered Institute of Procurement & Supply
- Procurement Act 2023, section 1: Procurement and covered procurement UK Parliament, The National Archives / UK Parliament
- Procurement Process CIPS, Chartered Institute of Procurement & Supply
- Institute For Supply Management CPSM ISM
- CPIM Learning System 2020 excerpt, Module 1: Basics of Supply Chain Management APICS, Association for Supply Chain Management (ASCM) / APICS
- Procurement Definition - What Is Procurement? CIPS, Chartered Institute of Procurement & Supply
- What is procurement? Definition, Types, Processes & More ASCM, Association for Supply Chain Management
- UNOPS Procurement Manual United Nations Office for Project Services
- Supply Chain Management Concepts CSCMP, Council of Supply Chain Management Professionals
- Sourcing CIPS, Chartered Institute of Procurement & Supply
- The ISM Glossary of Key Supply Management Terms Institute for Supply Management
- About ISM Institute for Supply Management
- Frequently Asked Questions CSCMP, Council of Supply Chain Management Professionals
- Levels of strategic purchasing: Impact on supply integration and performance Antony Paulraj; Injazz J. Chen; James Flynn, Journal of Purchasing and Supply Management 12(3), 107-122
- Developing a Consensus Definition of Supply Chain Management: A Qualitative Study James R. Stock; Stefanie L. Boyer, International Journal of Physical Distribution and Logistics Management
- Towards a unified definition of supply chain management: the four fundamentals Edward Sweeney, International Journal of Applied Logistics 2(3), 30-48
- Reflecting on the past 25 years of the Journal of Purchasing and Supply Management: the editors’ perspectives G. Zsidisin; R. Lamming; C. Harland; F. Wynstra; A. Ancarani; W. Tate; L. Knight and colleagues
- Purchasing-driven sales: Matching sales strategies to the evolution of the purchasing function Bert Paesbrugghe; Deva Rangarajan; Arun Sharma; Niladri Syam; Subhash Jha and colleagues, Industrial Marketing Management 62, 171-184
- Cross-functional integration and functional coordination in purchasing and supply management: Antecedents and effects on purchasing and firm performance K. Foerstl; E. Hartmann; J. Y. F. Wynstra; R. Moser, International Journal of Operations and Production Management 33(6), 689-721
- Section 16 - Eligibility and conditions for taking input tax credit, Central Goods and Services Tax Act, 2017 Central Board of Indirect Taxes and Customs
- MSME SAMADHAAN - Delayed Payment Monitoring System Ministry of Micro Small and Medium Enterprises Government of India
- Public Procurement (Preference to Make in India), Order 2017 - Revision, No. P-45021/2/2017-PP (BE-II)-Part(4)Vol.II dated 19 July 2024 Department for Promotion of Industry and Internal Trade Ministry of Commerce and Industry Government of India
- Total cost of ownership purchasing of a service: The case of airline selection at Alcatel Bell Zeger Degraeve; Eva Labro; Filip Roodhooft, European Journal of Operational Research 156(1), 23-40, 2004
- Constructing a Total Cost of Ownership supplier selection methodology based on Activity-Based Costing and mathematical programming Z. Degraeve; Eva Labro; F. Roodhooft, Accounting and Business Research 35(1), 2005
- Strategic purchasing, supply management, and firm performance Injazz J. Chen; Antony Paulraj; Augustine A. Lado, Journal of Operations Management 22(5), 505-523
Published by scimin, a product of Pralok Enterprise, Mumbai. scimin sells supply chain planning software and services. This article was researched and drafted with AI assistance. Every sourced figure links to the page it was checked against. Spot an error? Tell us and we will correct it with a dated note. How we write and check our articles.