Inventory control in supply chain management, without the jargon.

Three decisions, one worked example, and the places where the standard formula quietly stops being true.

scimin39 minute read

A saw-tooth stock diagram: stock falls, crosses a reorder line, keeps falling through the lead time, then the delivery restores it. The second delivery runs late, so stock drops into the safety stock band.Stock falls from a peak, crosses a dashed reorder line where the order is placed, and keeps falling through the lead time until the delivery returns it to the peak. The first cycle lands on top of the shaded safety stock band. The second delivery runs late, so the stock falls into the band before it arrives, which is what the band is there for.Reorder pointSafety stockLead timeOrder placedDeliveryStock falls. You order at the line.The buffer absorbs being wrong.Schematic, not measured data.
The whole subject in one picture. The first cycle behaves. The second delivery runs late, the stock drops into the buffer, and nobody goes short, which is the only thing the buffer is for.
Read the diagram

A line falls steadily from a peak, crosses a horizontal dashed line labelled Reorder point, and continues falling through a bracketed lead time until a delivery returns it to the peak. A shaded band along the bottom is labelled Safety stock. In the first cycle the stock lands on top of that band. In the second the delivery runs late, so the line falls into the band before recovering, the case the band exists to cover.

What is inventory control in supply chain management?

Inventory control is the set of decisions that determine how much stock you hold and when you replace it. The professional body defines it as the activities, systems and procedures used to optimize an organization’s inventory levels, and places it inside the wider discipline: Inventory control is an element of inventory management (ASCM). The distinction it draws elsewhere is about scope: inventory control focuses on the movement of products within a specific warehouse, while inventory management tracks stock across the whole organisation (ASCM).

In practice it comes down to three numbers per item. How much to order. When to order it. How much buffer to carry so that being wrong about either is survivable. Everything else in the vocabulary (cycle stock, safety stock, reorder point, economic order quantity, ABC, fill rate) is a name for part of one of those three.

They are not equally hard. One is forgiving to the point that precision is wasted effort. One is where almost all the money is, and where the standard formula quietly stops being true. And one is routinely measured against a target that means three different things.

On this page

1. How much to order: the economic order quantity, and why it forgives you.

Order in big batches and you hold more stock than you need. Order in small ones and you pay the ordering cost more often. The economic order quantity is the point where those two curves cross.

The model is 113 years old. Harris published it in February 1913 in Factory, The Magazine of Management (Erlenkotter), and it assumes a great deal: later work summarises it as assuming that the demand rate (“movement”) was known and constant, shortages were not allowed, and replenishments were instantaneous (Andriolo, Battini, Grubbström and colleagues). None of those is true of your business.

It barely matters, and this is the useful part. The order quantity that minimises cost is Lemma 5 (Economic Order Quantity): Q∗ = √(2Kd/h), with order cost K, demand rate d and holding cost h. The cost penalty for getting it wrong is governed by Lemma 7 (Sensitivity to Q∗). Let Q > 0 ... C_r(Q)/C_r(Q∗) = (1/2)(Q∗/Q + Q/Q∗) (Rossi, Inventory Analytics). That expression is almost flat near the bottom. Order 25% less than the formula says and you pay 4% more. Order double and you pay 25% more. As Dobson puts it, the model is well known to be somewhat insensitive to the choice of order quantity (Dobson).

Cost of ordering the wrong quantity, as a share of the best possible cost

0.5x
125%
0.75x
104.2%
1x (the formula)
100%
1.5x
108.3%
2x
125%
The three middle bars are barely above the best possible cost. That is why a convenient order quantity, whether a full pallet or a month’s cover or the supplier’s minimum, usually costs almost nothing. Computed from Lemma 7 in Rossi, Inventory Analytics, Open Book Publishers, CC BY 4.0: the cost ratio is half the sum of Q∗/Q and Q/Q∗. Covers only the ordering and holding costs the model includes.

There is a second reason not to agonise. The formula needs a holding cost, and nobody knows what that is. One review reports that Several authors have suggested that the value of IHC ranges between 12-50% of the procurement cost of an item, and explains the spread by the absence of a generally acceptable methodology (Odedairo, Alaba and Edem). A survey of Iowa manufacturers found a response by 82% of the manufacturers surveyed that they do not use inventory carrying cost to make purchasing and holding decisions at all, alongside a marked difference in carrying cost components reported by authors and manufacturers (Harms). The sample size is not given in the published abstract, so read it as an indication rather than a measurement.

So the formula is forgiving in exactly the dimension where its input is unknowable. That is a happy accident, and you should take it.

What to do about the order quantity.

Round to something operationally convenient and move on. A full pallet, a full container, the supplier’s minimum, a month’s cover. If you want a rule with a published bound: ordering on a cycle that doubles (weekly, fortnightly, monthly, quarterly) costs at most about 6% more than the theoretical best, by Lemma 9 (Powers-of-two bound): F(Tb2^k)/F(T∗) ≤ 3/(2√2) ≈ 1.06 (Rossi). Pick the convenient cycle. Spend the time you saved on the next section.

2. When to order: how to calculate a reorder point.

The reorder point is the stock level at which you place the order. It has to cover demand over the lead time, plus a buffer for demand being higher than average. The textbook form is R = µL + zσ√L: average demand per period µ, lead time L, standard deviation of per-period demand σ, and a safety factor z from the service level you want (MIT 15.762J notes, Willems, from lecture notes by Graves).

One thing to get right before the arithmetic: the trigger is inventory position, not what is on the shelf. Position is IP = Inventory Position = (IOH) + (Inv On Order) - (Backorders) - (Committed) (Caplice, MIT ESD.260). Trigger on stock on hand alone and you will order again every day while the first order is still in transit.

Cycle service level, fill rate or ready rate: which 95% do you mean?

A service level is at least three different promises, and the one you mean changes the number. Cycle service level is the probability that an order arrives on time, i.e. that no stock-out occurs in a replenishment cycle (Prak, Teunter and Syntetos); it says nothing about how much you were short when you ran out. Fill rate determines the percentage of demand satisfied directly from stock-on-hand and is the most commonly used measure in industry; it is not the same as the order fill rate, which represents the fraction of complete orders that can be filled directly from stock, and neither is the ready rate, specified as the fraction of time during which the stock-on-hand is positive (Teunter, Syntetos and Babai).

They coincide only under particular assumptions: for pure Poisson and normally distributed demand the (volume) fill rate is equivalent (although only approximately in the case of the normality assumption) to the ready rate (Teunter, Syntetos and Babai). The z below is a cycle service level. Hold onto that: in section 3 it turns out to decide which way the advice points.

Picking z is the only part of this that comes out of a table rather than your own data. These are the values the standard normal distribution gives for the service levels firms actually set, with what each would mean for the SKU worked below:

Cycle service level z Safety stock on the worked SKU
90% 1.28 49 units
95% 1.65 63 units
97.5% 1.96 74 units
98% 2.05 78 units
99% 2.33 88 units
99.9% 3.09 117 units

Note what the bottom row costs. Going from 95% to 99.9% nearly doubles the buffer to buy under five percentage points of cycle service, and that is before any of the corrections below. In a spreadsheet the z column is =NORM.S.INV(0.95), which Returns the inverse of the standard normal cumulative distribution (Microsoft); the values here are computed that way and agree with the standard normal table printed in Bricker’s slides at the points both cover.

A worked example: the reorder point for one SKU.

A distributor sells a line at an average of 40 units a day, with a daily standard deviation of 12. The supplier takes 10 days. Target: a 95% cycle service level, so z is about 1.65 (Bricker, University of Iowa).

  • Expected demand over the lead time: 40 × 10 = 400 units
  • Safety stock: 1.65 × 12 × √10 = 63 units
  • Reorder point: 400 + 63 = 463 units

That is where almost every article on this subject stops, and it is wrong twice over: once because σ is an estimate rather than a known quantity, and once because the lead time is a distribution rather than the number 10. Both corrections belong to the buffer, which is the next section.

What to do about the reorder point.

Record two dates on every receipt: when you asked for it, and when it arrived. Nothing else you can do this month will tell you more. You may not need a new process for it: if purchase orders and goods receipts are already dated in your system, the distribution can be rebuilt from last year’s data this afternoon, with nobody’s permission. Without it the reorder point is computed from an assumption rather than an observation.

3. How much safety stock do you actually need?

Sections 1 and 2 were quantity and timing. The buffer is the third decision, the one that absorbs being wrong about the other two, and it is where almost all of the money is.

Section 2 left a safety stock of 63 units and two reasons not to believe it.

Why safety stock needs a forecast-error correction.

σ is estimated, and the formula pretends it is not. The standard approach takes the per-period demand variance and multiplies it by the lead time. Prak, Teunter and Syntetos state the practice and then demolish it: However, this is flawed, since forecast errors for different periods of the lead time are positively correlated, even if the demand process itself does not show (process) auto-correlation. Every period’s forecast error contains the same estimation error, so they do not cancel the way independence assumes. (Why those errors are there at all, and which of them are worth attacking, is the subject of its own article.) Their correction multiplies the safety stock by M_sigma = sqrt((L.sigma^2 + L^2.Var(Y-hat_N))/(L.sigma^2)) = sqrt(1 + L.Var(Y-hat_N)/sigma^2), and for an exponentially smoothed forecast the ratio inside has a closed form, Var(Y-hat_N)/sigma^2 = alpha/(2-alpha) (Prak, Teunter and Syntetos).

With a smoothing constant of 0.2 that multiplier is √(1 + 10 × 0.111) = 1.45, so the safety stock goes from 63 to 91 units (Prak, Teunter and Syntetos). Their own simulations put the general cost of ignoring this at traditional approaches can lead to safety stocks that are up to 30% too low and service levels that are up to 10% below the target. Note the scope. The correction is derived for inventory systems with a constant lead time where demand fluctuates around a constant level, and the figures are simulation results rather than measured operations.

The reorder point formula when the lead time varies.

The lead time is not 10 days. It is 10 days on average. Once the lead time varies too, σ²L is the wrong variance. Demand over a variable lead time is a random sum, and its variance has a second term: the lead time’s own variability multiplied by the square of average demand. NetSuite’s documentation prints the form you want: Lead-Time Demand Standard Deviation = sqrt(Average Lead Time * Daily Demand Standard Deviation^2 + Average Daily Demand^2 * Lead-Time Standard Deviation^2) (Oracle NetSuite).

Check any version of this you meet, because the wrong one is in circulation. Set the lead-time variability to zero: a correct form has to collapse back to σ√L, the textbook answer. This one does: √(10 × 12²) = 38, which is 12 × √10. A form carrying the square of the average lead time in that first term returns σL instead, 120 units here rather than 38, and inflates every safety stock computed from it. Now give the supplier a standard deviation of three days:

Running that through: 10 × 12² + 40² × 3² = 1,440 + 14,400 = 15,840, so the standard deviation of demand over the lead time is √15,840 = 125.9, and the safety stock at the same 95% target becomes 1.65 × 125.9 = 208 units, for a reorder point of 608 (Oracle NetSuite).

Safety stock for one SKU, same demand, three assumptions

Safety stock in units

Textbook formula
63
Forecast error counted
91
Lead time varies by 3 days
208
Same item, same demand, same 95% target. The third bar is what the supplier’s reliability costs, and it is larger than everything the first two bars argue about. Worked from the example in the text at 40 units/day, standard deviation 12, lead time 10 days, z = 1.65. The third bar assumes the lead time itself has a standard deviation of three days. Correction multiplier from Prak, Teunter and Syntetos at a smoothing constant of 0.2; variable lead-time variance as published by Oracle NetSuite. Illustrative figures, not measured from any firm.

Sixty-three units, ninety-one, two hundred and eight. Same item, same demand, same target.

Look at the two terms in that last sum (Oracle NetSuite). The customer’s variability contributes 1,440; the supplier’s contributes 14,400. Ten to one, but that ratio is set by the three days, which was an assumption, not a measurement. The two terms are equal at a lead-time standard deviation of about one day (10 × 12² = 40² × 0.95²). So the real question is only whether your supplier beats one day, and almost nobody knows, because the two dates it takes to find out are not being recorded. That is why it is step 1 below rather than a conclusion here.

Now put the three answers side by side and price them. The unit counts are the arithmetic above. The ₹500 landed cost and the 20% gross margin are illustrative figures chosen to make the comparison concrete, not measured from any firm; the 0.75% a month is the cost of money from section 6, before storage, insurance, handling and obsolescence.

What you assume Safety stock Reorder point Extra stock vs the textbook Cost of carrying it
Lead time fixed at 10 days, σ known exactly 63 units 463 None None
…plus the forecast’s own estimation error 91 units 491 28 units ₹105 a month
…plus a lead time that varies by 3 days 208 units 608 145 units ₹544 a month
Both corrections at once, approximately 218 units 618 155 units ₹581 a month

The two corrections are not the same size. Counting the forecast’s own error adds 28 units. Admitting that the supplier is sometimes late adds 145. The correction the literature argues about is the smaller one by a factor of five, and the larger one is missing from the formula most planners were taught.

The literature does not fully endorse any of this. Eppen and Martin showed that the standard way of setting safety stock when demand and lead time are both random is not a safe approximation: examples are used to show that this procedure can yield results that are far from the desired result. A correct procedure is presented. (Eppen and Martin). Their objection is to treating lead-time demand as normal with a plugged-in variance, which is what the third row does. The row is still a far better guide than the first, because the term it adds is real and large; treat it as an argument for measuring your supplier rather than as a number to trust to the unit.

And nobody tells you how to apply both corrections at once. The last row is arithmetic, not a result. Prak, Teunter and Syntetos derive their correction for a fixed lead time (Prak, Teunter and Syntetos), so stretching it over the variable-lead-time variance is an approximation of mine: inflate the demand variance by the square of that factor, since 1.45 corrects a standard deviation: 10 × 12² × 2.11 + 40² × 3² = 17,440, and the safety stock becomes 1.65 × √17,440 = 218 (Oracle NetSuite). Treat it as an indication of size, not a number to put in a system. If you want one defensible figure, use the third row, because the term it adds is the big one.

The money is smaller than the argument, and so is the saving. Carrying 145 more units of a ₹500 item costs about ₹544 a month at the cost of money alone (Reserve Bank of India). That is the floor, not the cost: the literature puts all-in holding cost between 12-50% of the procurement cost of an item, with 25% the figure most often cited (Odedairo, Alaba and Edem), which puts the same buffer nearer ₹1,510 a month.

Now price what the buffer saves, which is less than it looks. The expected shortfall in a cycle is G(R) = sigma x L((R - mu)/sigma) (Bricker, University of Iowa): the standard deviation of lead-time demand times the unit normal loss function. At z = 1.65 that function is 0.0206, so this SKU expects to be short about 2.6 units in a cycle, not 145. Landed at ₹500 and sold at ₹625 (a 20% gross margin, so ₹125 a unit), that is roughly ₹325 of margin at risk per cycle against ₹544 to ₹1,510 a month of carrying cost.

Which means the buffer is not paying for itself in units of lost sale, and on these figures it is larger than the arithmetic alone would justify. What it buys is the occasions: at a 95% cycle service level you breach in one cycle in twenty (Bricker, University of Iowa), and the question is what a breach costs you. If it costs you the order, this buffer is too big. If it costs you the customer, no buffer this size is expensive. That is the judgement the formula cannot make, and it is the one worth your attention, not the third decimal place of σ.

And which service level you meant can reverse the advice. This is where the distinction from section 2 stops being pedantry. Chopra, Reinhardt and Dada show the existence of a service level threshold greater than 50 percent below which re-order points increase with a decrease in lead time variability: below that threshold, making your supplier more consistent requires you to hold more, not less, and the normal approximation gets the sign wrong. In a worked case of theirs, cutting the lead-time standard deviation moves the exact answer the opposite way from the approximation: The exact calculation, however, shows that reducing the standard deviation of lead time increases the required safety stock from 20 to 22.

On their worked figures the threshold lands somewhere in the region of a 0.5 to 0.7 cycle service level, a band that corresponds to the high fill rates firms commonly target, though the paper states the threshold’s existence rather than a universal value for it. So the trap is exactly the confusion in section 2. You set a number thinking it is one measure, the formula treats it as another, and in that band its advice is backwards. Their conclusion is that the normal approximation erroneously encourages managers to focus on reducing the variability of lead times when they would be better of reducing the lead time itself (Chopra, Reinhardt and Dada); the typo is theirs. At a genuine 95% cycle service level, as in the table above, the approximation points the right way.

One more habit to drop. Setting every item’s service level to the company target is, in the authors’ words, The typical approach utilized in practice, and suggested in academic textbooks, and it is far from optimal, because the total fill rate is a demand-weighted average of the individual ones: FR_T = (sum_{i=1}^{N} FR_i . D_i) / (sum_{i=1}^{N} D_i) (Teunter, Syntetos and Babai). Your fast movers carry the company number. Your tail does not need to.

What to do about the buffer.

Write down which measure your 95% is, once, and put it at the top of the report: the customer experiences the fill rate (Teunter, Syntetos and Babai), and if the two have never been compared, that is the first thing to find out. Then recompute the buffer with the lead-time term in it, because on the table above that is the row that moves.

4. Why the inputs break the formula: wrong stock records, censored demand.

Everything above assumes you know your demand and your stock. Both assumptions are shakier than the mathematics.

Your demand history is censored. The weeks you sold nothing because you had nothing look identical to the weeks nobody wanted it, because what the system recorded was sales and what the formula needs is demand. The series that justifies safety stock is missing exactly the periods that justify it.

Your stock figure is probably wrong. Examining nearly 370,000 inventory records across 37 stores of one retailer, DeHoratius and Raman found 65% to be inaccurate (DeHoratius and Raman). The same research programme reports that misplaced stock prevented one in six customers who requested help from a sales associate from finding the products that were available in a store, and that These execution problems reduce profits by more than 10% (Raman, DeHoratius and Ton). That is one study reported twice, not two independent findings.

And the parameters are mostly guesses that nobody revisits. Across 84 Swedish manufacturers, The most common ways to determine planning parameters are based on judgement and experiences and The majority of companies review the parameters less frequently than once a year (Jonsson and Mattsson).

That last finding is the practical one. If the parameter is reviewed once a year, the precision of the formula that set it is not what is limiting you.

5. What inventory control software actually calculates.

Most of this is moot if the system you own does not implement it. The documentation is clearer on this than the sales material.

Does Odoo’s reordering rule include safety stock?

No. Odoo’s documented reordering rule has no safety stock in it. The rule is used to keep forecasted stock levels above a certain threshold without exceeding a specified upper limit, where the threshold is just Min: The minimum quantity that can be forecasted without the rule being triggered. (Odoo). Your Min is your safety stock, and nothing will work it out for you.

What does TallyPrime’s reorder level do?

TallyPrime holds a reorder level you set and does the comparison for you, reporting the gap against net availability: Only when the quantity in Re-order Level column is more than the Nett Available column, the difference appears as a shortfall (Tally Solutions). What it never uses is a service level, a standard deviation or a demand distribution.

What is BUSY’s Critical Level?

BUSY calls the same idea a Critical Level, lets you configure the required critical levels and define them warehouse-wise where applicable, and will block a transaction outright (BUSY). It will also specify the number of days before expiry when BUSY should provide a warning, though the operator still has to select the batch from which stock will be issued (BUSY), so first-expiry-first-out is a discipline rather than a setting.

How does SAP calculate a reorder point?

SAP computes properly. Its automatic reorder point planning sets out to Calculate safety stock and reorder point using forecast from the Service level, defined in the material master record and the Mean absolute deviation calculated during the forecast run (SAP). Note that it uses mean absolute deviation, not the standard deviation the textbook formula wants.

Does Dynamics 365 calculate safety stock?

Dynamics 365 calculates a proposed minimum quantity based on an item’s historical usage, with an explicit service-level path: Use service level - Select this option to calculate a proposed minimum based on the desired service level., though you must first enable the standard deviation calculation (Microsoft).

What does NetSuite store, and what does it compute?

NetSuite’s base item record only stores a typed number: Safety Stock Level - Represents the amount of stock to keep on hand to account for demand variations so that you don’t run out. Its separate Inventory Optimization module computes one, and publishes the formula: Reorder Point = Safety Stock Level + (Average Lead Time * Average Daily Demand), with a lead-time demand standard deviation that correctly includes both sources of variability (Oracle NetSuite).

How do you calculate a reorder point in Excel?

The function you want is NORM.S.INV, which Returns the inverse of the standard normal cumulative distribution (Microsoft). Feed it 0.95 and it returns 1.645. Change the 0.95 and you have changed your service level, which is the one place in all of this where the arithmetic is genuinely easy.

If this is the section that decided something for you, the longer version of the question (what to ask a vendor, and what the answers mean) is in how to choose supply chain planning software in India.

6. What does holding inventory cost in India?

The number that makes this concrete is the cost of money. Across scheduled commercial banks the one-year median marginal cost of funds based lending rate stood at 8.70 per cent in August 2026 (8.60 per cent in July 2026), and the weighted average rate on loans already outstanding was 8.97 per cent in July 2026 (8.96 per cent in June 2026) (Reserve Bank of India). Call it 9% before you add storage, insurance, handling and obsolescence.

Nine per cent a year (Reserve Bank of India) is about 0.75% a month on the money tied up. Set that against the margin on the item. Holding an extra month of cover costs you three-quarters of one per cent of its cost; running out costs you the margin on whatever the customer buys from somebody else, and sometimes the customer. That is the comparison to make, and it runs against the instinct this whole subject encourages.

How much do Indian firms actually hold? I could not find an official aggregate worth quoting, so here are five listed companies taken from their own filings, each one computed from the inventory and revenue they reported (Britannia).

Inventory as a share of revenue, five Indian firms, FY2025-26

Britannia
7%
Ajanta Pharma
17.2%
Dabur
17.6%
Torrent Pharma
22.4%
Cipla
23.4%
A threefold spread, and what the companies sell explains more of it than how well they run: two pharmaceutical names at the top, packaged foods at the bottom, and one FMCG company sitting inside the pharma range. Which is why a single national benchmark would mislead you. Inventories and revenue from each company’s own FY2025-26 exchange filing (NSE integrated filings; Dabur from its published consolidated financials). Ratios derived, not disclosed by the companies. Four are large listed firms and Ajanta is a mid-cap, so none is a true mid-market comparator; three of the five are pharmaceutical.

Two structural facts shape where Indian firms hold stock.

Moving goods worth more than fifty thousand rupees needs an e-way bill: the rule applies to Every registered person who causes movement of goods of consignment value exceeding fifty thousand rupees (CBEC Notification 27/2017), and it applies whether the movement is in relation to a supply or for reasons other than supply, which catches your own stock transfers (Directorate General of Taxpayer Services, CBEC).

Each GST registration of one company is treated as a separate entity: a business with more than one registration, whether in one State or Union territory or more than one State or Union territory shall ... be treated as distinct persons for the purposes of GST (CBEC). Moving your own stock across a state line is therefore a transaction, not a transfer.

And for food and pharma, the expiry date is a cliff rather than a slope. FSSAI defines a use-by date as one after which the product may not remain safe and the food, shall not be sold or distributed for human consumption (FSSAI). A best-before date is a markdown decision. A use-by date is a write-off, and your safety stock on a short-dated line is buying insurance that expires.

7. How to measure inventory performance, and why benchmarks mislead.

Inventory turns look like a universal number. They are not, because the numerator is not standardised. Advance Auto Parts defines its own as Inventory turnover is calculated as cost of sales divided by the average of beginning and ending inventories. On its FY2011 figures, Net Sales: $6,170,462 ... Cost of Sales: $3,101,172 ... Gross Profit: $3,069,290 ... Inventories: $2,043,158 (Advance Auto Parts 10-K), cost of sales against that closing inventory gives 1.52 turns. Use revenue instead, on the identical inventory, and the same company turns 3.02 times. One balance sheet, two defensible methods, a factor of two apart. Both are computed here on the closing figure rather than the company’s own average of opening and closing, which needs a number this excerpt does not carry; the ratio between the two conventions does not depend on that choice.

One balance sheet, two defensible turnover figures

Inventory turns per year

Cost of sales
1.52
Revenue as the numerator
3.02
Neither is wrong. They are different conventions, and a benchmark that does not say which one it used cannot be compared with yours. Computed from Advance Auto Parts’ FY2011 10-K: net sales $6,170,462k, cost of sales $3,101,172k, closing inventories $2,043,158k. Both figures use the closing inventory. The convention the company states for its own reporting is the cost-of-sales one. See the filing.

Even with a consistent method, the comparison is weak. Across 311 US retailers, Inventory turnover varies widely across retailers and over time. This variation undermines the usefulness of inventory turnover in performance analysis, benchmarking and working capital management. A model using gross margin, capital intensity and sales surprise explains 66.7% of the within-firm variation and 97.2% of the total variation (Gaur, Fisher and Raman). The same authors put the problem as a question worth keeping: might we reasonably conclude that Kroger managed its inventory better than Gap? (Fisher, Gaur and Raman).

The classification schemes have the same quality. ABC dates to 1951 and The ABC system of inventory control was developed in 1951 by H. Ford Dickie of General Electric. The familiar cut comes with a caveat the retellings drop. Walter offers it as one reasonable breakdown among several rather than a rule, naming the A category as the 20 percent of the total items carried which contribute the top 80 percent of sales (Walter). A later paper uses entirely different cuts, group A includes 5% of the items that represent 75% of value-usage (Santos, Ferreira and colleagues), and ranks on cost times annual demand rather than sales. More usefully, applying fixed service levels by class leads to solutions that are far from cost optimal (Teunter, Babai and Syntetos).

The intermittent-demand cuts deserve the same scepticism, and the reason is quietly devastating. The standard scheme splits items by average inter-demand interval and demand variability compared with cutoffs of 1.32 for ADI and 0.49 for CV2 (Ramaekers and Janssens). Those numbers are not facts about demand. As one review puts it, Thresholds were set based on empirical findings regarding where the methods proposed by Croston (1972) and Syntetos and Boylan (1999, 2001) performed best. (Rozanec and Mladenic). They mark where one forecasting method starts beating another. A paper examining the boundaries concludes that the choice of boundaries between categories should depend on the sector and type of item (Babiloni, Cardós and colleagues).

8. Inventory control methods, and which decision each one serves.

Most of the vocabulary in this field is not a fourth decision. It is a name for a way of making one of the three, or for keeping their inputs honest. Here is each method you are likely to be sold, what it is, and which of the three it touches.

What is the difference between periodic and continuous review?

It is the difference between watching and checking. In a continuous review system, the time between orders varies but the amount ordered is fixed; In a periodic review system, the time between orders is fixed but the amount ordered varies (MIT 15.762J notes, Willems, from lecture notes by Graves). Continuous review is the policy section 2 described: watch inventory position, order a fixed quantity when it hits the reorder point. Periodic review looks on a cycle and orders back up to a level: Order S-IP every R time periods (Caplice, MIT ESD.260).

Which decision: when to order, and it quietly changes the buffer. The same notes give the periodic form as B = (r+L)µ + zσ√(r+L) with Safety stock = zσ√(r+L) (MIT 15.762J notes, Willems, from lecture notes by Graves). The square root now covers the review interval as well as the lead time. Put the worked SKU on a weekly review: 1.65 × 12 × √17 = 82 units of safety stock instead of 63.

But the larger cost is the second term the same source prints, Cycle stock = rµ/2: a weekly cycle on 40 units a day is 140 units of stock held for no reason except the review calendar.

Safety stock for one SKU as the review interval lengthens

Safety stock in units

Continuous
63
Weekly
82
2-weekly
97
4-weekly
122
The same item and the same 95% target. Nothing about the demand or the supplier has changed, only how often somebody looks. Computed as zσ√(r+L) with z = 1.65, σ = 12 units/day, L = 10 days, from the periodic-review form given in MIT 15.762J notes, Willems, from lecture notes by Graves. Illustrative figures, not measured from any firm.

Continuous review is Able to provide same level of service with less safety stock; its cost is the Cost of equipment and the honest question the slide itself asks, Is continuous really continuous? (Caplice, MIT ESD.260).

One warning about the words. In bookkeeping, periodic and perpetual mean something else entirely: when the inventory account is updated, not when orders are placed. A perpetual inventory system automatically updates and records the inventory account every time a sale, or purchase of inventory, occurs, while A periodic inventory system updates and records the inventory account at certain, scheduled times at the end of an operating cycle (OpenStax). Your accountant and your planner can use the same two words about the same company and not be discussing the same thing.

What is a min-max system, and is that the same as a two-bin system?

Min-max is a reorder point with a ceiling. An inventory system that is controlled by an (s, S )-replenishment policy is also known as a min-max system, where Under the (s, S ) control, a replenishment order is placed to raise the inventory position (= on-hand stock + outstanding orders − backorders) up to S whenever it drops to s or below (Project Production Institute). The formal name is the mouthful: These ordering policies are called (s,S) policies or reorder point, order-up-to-level policies, and there is a shortcut from what section 2 already gave you: One approximation is to compute a (Q,R) policy and set s=R and S=R+Q (Bilkent University, IE375).

A two-bin system is the same idea implemented in sheet metal: two-bin system - Two containers of inventory; reorder when the first is empty (Stevenson glossary, McGraw-Hill). Whether it is the same policy is a question the sources do not agree on, so treat the terms as local rather than standard. Britannica says The two-bin system (sometimes called the min-max system) involves the use of two bins, either physically or on paper (Encyclopaedia Britannica), while MIT files Two-bin system under Order-Point, Order-Quantity (s, Q) and Continuous Review (R=0), listing order-up-to as a separate policy (Caplice, MIT ESD.260). Ask which one a vendor means before agreeing to it.

Which decision: when to order, plus how much, bundled into one rule.

What is just-in-time inventory, and when does it work?

Just-in-time is the decision to remove the variability rather than pay to cover it. That is why it is not a buffer policy you can switch on: it has preconditions. The conditions for a JIT segment include minimum fluctuations in demand, matching manufacturing cycle times across the nodes in the segment, and proximity of these nodes, which makes short transit times and close collaboration possible at various levels of the companies in the link (Choi, Netland, Sanders and colleagues). Read that against section 3: minimum fluctuations in demand and short transit times are precisely the two terms that drive the safety stock formula. JIT attacks the inputs, which is the only way the buffer legitimately goes to nearly nothing.

Where the preconditions fail, it is measurable. Across US listed manufacturers, a one standard deviation increase in the supply chain pressure index is associated with a roughly 2.3% stronger decline in sales among JIT firms, and in the author’s model The total output loss in the JIT economy along the transition back to steady state is 3.8% while it is 2.3% in the counterfactual economy (Ortiz). The same paper blocks the easy conclusion: Moreover, a transition to an equilibrium with less JIT and larger inventory buffers leads to a roughly 4% output loss. Holding more is not free either.

Which decision: the buffer, by changing what the buffer has to cover.

What is vendor-managed inventory?

VMI is a supply chain strategy where the vendor or supplier is given the responsibility of managing the customer’s stock, under which the customer passes inventory information and Point of Sales (POS) data to their suppliers rather than placing replenishment orders (Disney and Towill). Note what moves and what does not: the decision moves, the ownership does not. VMI refers to the tasks associated with managing the inventory provided by the supplier on the other hand consignment relates to the ownership of the inventory (Rana and colleagues); consignment is the separate arrangement in which the vendor retains the ownership of the inventory and gets paid by the retailer on actual units sold (Bieniek). Signing a VMI agreement expecting your stock to leave the balance sheet is the common mistake.

What it delivers, measured across firms rather than simulated: VMI leads to three performance outcomes: higher customer service levels, improved supply chain control and, to a lesser extent, cost reduction, and the same study provides empirical evidence of why VMI in practice does not achieve all the benefits claimed in theory (Claassen, van Weele and van Raaij).

Which decision: all three, handed to the supplier. Which, on section 3’s arithmetic, is the interesting part: the term that dominated the buffer was the supplier’s own variability, and VMI is the arrangement that makes it their problem to manage rather than yours to absorb.

What is cycle counting?

Counting a slice of the catalogue continuously instead of everything once a year, with the frequency tied to how much the item matters: Class “A” items are counted more frequently than “B” items and class “B” items are counted more frequently than class “C” items, where Typical count frequencies are 4 times per year for class A, 2 times a year for class B, and once a year for class C items (Rossetti, Collins and Kurgund).

The goals are diagnostic, not clerical: to identify the causes of errors, to correct the conditions causing the errors, to maintain a high level of inventory record accuracy, and to provide a correct statement of assets, and the review concludes that cycle counting is clearly the dominant method and best practice for maintaining inventory record accuracy, reporting that inventory record accuracy above 95% can be consistently maintained (Rossetti, Collins and Kurgund).

Counting by value class is contested: Orozco [24] makes a strong case against ABC cycle counting based on the argument that inventory record errors can only be introduced when an inventory transaction occurs, the alternative being that counting is scheduled based on the number of transactions experienced by a SKU (Rossetti, Collins and Kurgund).

And an accuracy percentage means nothing without the tolerance it was measured at: inventory accuracy is defined as the ratio of the total number of accurate records to the total number of records examined, with APICS [1] recommends that class A, B, and C items have tolerance of 0.5%, 1%, and 5% respectively (Rossetti, Collins and Kurgund). The same retailer data behind section 4 illustrates how much that choice moves the number: the best performing store is the one in which only 70%-75% of its inventory records match the actual inventory. On average, the inventory accuracy of Company A stores is only 51% (Kang and Gershwin, MIT 2.854).

Which decision: none of them. It repairs the input all three run on: the stock figure that section 4 found wrong in 65% of records (DeHoratius and Raman).

What is FIFO, and how is FEFO different?

Both are issue-order rules: they decide which unit leaves, not how many you hold. The question is old and has an answer: across most of the objective functions studied, the optimal policy is to issue the oldest unit which will satisfy the demand (Pierskalla and Roach). FIFO reads age from the receipt date. FEFO reads it from the expiry date: A distribution procedure that ensures that the stock with the earliest expiry date is distributed and/or used before an identical stock item with a later expiry date is distributed and/or used (WHO Technical Report Series 1025, Annex 7), which means the earliest expiry date are issued/used first, regardless of the date of receipt (NHSRC-hosted guidance).

For anything dated, those two rules disagree whenever a shipment arrives with a shorter remaining life than the stock already on the shelf, and FIFO is then the one that writes stock off. The WHO annex expands the acronym two different ways in the same document, as first expiry/first out and first expired/first out, so do not read much into the wording.

Which decision: none of the three. It governs issue order, and section 5 is where it becomes a software question rather than a policy one.

What are ABC, VED and FSN analysis?

Three ways of deciding which items deserve attention, differing only in what they rank on. ABC ranks on money. VED ranks on consequence of absence. FSN ranks on movement: Total of 136 drug items were categorized by FSN analysis according to inventory turnover rate as fast, slow and non-moving groups, with the cut made against the observed average rather than a standard threshold: Drugs which have turnover rate higher and lower than average turnover rate were classified into fast and slow-moving items, respectively. Ones which have no inventory turnover rate or turnover rate approximately equal to zero were regarded as non-moving or dead stock (Hlaing and colleagues).

The reason to combine them is that each one alone is blind in a specific way: ABC analysis consider only monetary value and VED analysis consider criticality of importance, ABC/VEN matrix is the most suitable inventory control technique use in hospital (the typos are the source’s) because Since ABC consider only high value items, vital drugs which utilize low monetary value will be omitted (Hlaing and colleagues).

Which decision: where you spend your own attention, not what the quantities should be. And as section 7 notes, converting a class directly into a service level leads to solutions that are far from cost optimal (Teunter, Babai and Syntetos). Classify to decide what to look at. Do not classify to decide what to hold.

None of these methods is an optimisation, and the word gets attached to all of them. What it actually means, and what it takes to do, is a separate question.

Limits: where this does not apply.

The safety stock mathematics here assumes demand is roughly normal. For slow-moving items it is not, and the standard alternative has its own problem: real intermittent demand is over-dispersed, so the traditional static Poisson distribution can be too restrictive for intermittent inventories... better predictions may be obtained from distributions which allow for over-dispersion (Snyder, Ord and Beaumont). If most weeks are zeroes, none of the formulas above is the right tool.

The forecast may not be the constraint. Testing the link directly, the efficiency of inventory systems does not relate directly to demand forecasting performance, as measured by standard forecasting accuracy measures (Syntetos, Nikolopoulos and Boylan). Sharpening the forecast is not automatically the way to better stock.

And the whole framing of inventory as a cost to minimise is contested. Where holding stock increases sales, iterating the standard order quantity yields an equilibrium order quantity that is robust to demand parameter misestimation, but is suboptimal, and the optimal policy yields significantly higher profits than cost-based inventory policies, underscoring the importance of profit-driven inventory management (Balakrishnan, Pangburn and Stavrulaki). For a distributor whose gross margin comfortably exceeds 9% a year, that is the more relevant frame.

Where to start.

In order of what it costs you to do:

  1. Build your lead-time distribution. Purchase order date against goods receipt date, for last year. It is usually already in the system. Within a quarter you will know your lead-time distribution, which is the term the formula most planners use leaves out entirely, and the one almost nobody measures. A day to set up.
  2. Decide which service level you mean, and write it on the report. Cycle service level or fill rate. An hour, and it stops two people optimising different things.
  3. Flag the stockouts in your sales history. Periods when you had nothing to sell are not periods of zero demand. Exclude or impute them before fitting anything. A day.
  4. Stop tuning the order quantity. Round to a pallet, a container or a convenient cycle. Reclaim the time.
  5. Recompute the reorder point with the lead time’s own variance, once you have step 1: (average lead time × demand variance) + (average demand² × lead-time variance), then take the square root. In the worked example this term was ten times the size of the demand term.
  6. Add the forecast-error correction if you reorder from a smoothed average: multiply safety stock by √(1 + Lα/(2 − α)). One cell.
  7. Demand-weight your service levels. The company fill rate is a demand-weighted average, so the lines that carry the volume have to carry the target and the tail does not. Start by splitting the catalogue in two by annual value rather than building a full ABC scheme.
  8. Re-review the parameters quarterly. In the one survey that asked, the satisfied users use more analytical approaches and review parameters more frequently than others (Jonsson and Mattsson). Both halves, not just the second.

The first six are days of work. The last is a calendar entry, and on the available evidence it is the one that separates the firms this works for from the firms that merely own the formula.

Frequently asked questions.

What is the difference between inventory control and inventory management?

Inventory control is the narrower of the two. The professional body describes inventory control as an element of inventory management, and distinguishes them by scope: control focuses on products within a specific warehouse, management tracks inventory across the whole organisation (ASCM). In day-to-day use most people mean the three decisions in this article.

How do I calculate a reorder point?

Average demand per period multiplied by the lead time, plus a safety buffer: R = µL + zσ√L, where z comes from your target service level and σ is the standard deviation of demand per period. For a 95% cycle service level z is about 1.65 (Bricker). Two caveats the standard version omits: if your lead time varies, use the combined variance (average lead time × demand variance) + (average demand² × lead-time variance) instead of σ²L, and if your forecast is a smoothed average, multiply the safety stock by √(1 + Lα/(2 − α)).

How much safety stock should I hold?

Enough to cover the gap between what you expect and what actually happens, over the time it takes to get more. In the worked example above the same SKU needs 63 units on the textbook formula, 91 once the forecast’s own estimation error is counted (Prak, Teunter and Syntetos), and 208 once the lead time varies by three days (Oracle NetSuite). On those figures the largest term is the supplier’s reliability rather than the customer’s. Measure your lead-time distribution before trusting any number.

Is EOQ still relevant?

As a way of seeing the trade-off, yes. As a number to implement precisely, not really. The cost penalty around the optimum is very flat: ordering a quarter less than the formula’s answer costs about 4% more on the costs the model covers, and a quarter more costs 2.5% (Rossi), and the holding-cost input it requires has no agreed method of calculation. Round to something operationally convenient.

What is a good inventory turnover ratio?

There is no portable answer, and comparing yours to a published figure is riskier than it looks. The ratio changes depending on whether the numerator is cost of sales or revenue, by a factor of one over one minus the gross margin, which was close to two for the retailer in section 7 but nearer 1.25 at a 20% margin, and across 311 retailers gross margin, capital intensity and sales surprise explained 97.2% of the total variation in turns (Gaur, summarising work with Fisher and Raman). Compare yourself to yourself over time, and state your method.

Can I do this in Tally or Excel?

Partly. TallyPrime holds a reorder level and flags a shortfall against net availability (Tally Solutions), but it has no concept of a service level or a demand distribution, so the statistical part has to happen outside it and come back in as a number you type. In Excel the piece you need is NORM.S.INV to turn a service level into a z value; everything else is arithmetic. That combination is enough for most mid-market catalogues.

My supplier is unreliable. Should I push them on consistency or on speed?

On speed, usually. Where the required service level is high, both help and consistency helps a great deal. But below a cycle service level threshold the paper puts somewhere in the region of 50% to 70% the exact calculation can reverse the usual advice, and the normal approximation erroneously encourages managers to focus on reducing the variability of lead times when they would be better of reducing the lead time itself (Chopra, Reinhardt and Dada). A shorter lead time shrinks every term in the formula at once.

Sources.

62 references

Published by scimin, a product of Pralok Enterprise, Mumbai. scimin sells supply chain planning software and services. This article was researched and drafted with AI assistance. Every sourced figure links to the page it was checked against. Spot an error? Tell us and we will correct it with a dated note. How we write and check our articles.

See it in the product: demand forecasting for automotive spares, demand forecasting for industrial MRO spares and how the forecast is built.

Talk to us about your inventory policy.

Related articles.